[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937678,606,1,"单选题","（2013年真题）对于政府直接投资的项目，政府的要求和期望不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量合格",false,{"key":16,"text":17,"correct":18},"B","松弛的工作进度",true,{"key":20,"text":21,"correct":14},"C","投资适当",{"key":23,"text":24,"correct":14},"D","符合国家规划","本题考查的是工程项目的主要利益相关方及其要求和期望。选项B 属于咨询内部各部门的要求和期望。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]