[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937674":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937674,606,1,"单选题","（2014年真题）工程项目目标系统的建立工作包括：①提出项目目标；②项目构思；③识别要求；④建立目标系统。正确的顺序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①-②-③-④",false,{"key":16,"text":17,"correct":14},"B","③-②-④-①",{"key":19,"text":20,"correct":14},"C","③-①-②-④",{"key":22,"text":23,"correct":24},"D","②-③-①-④",true,"本题考查的是工程项目管理的基本原理。目标系统的建立过程为：工程项目构思→识别需求→提出项目目标→建立目标系统。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]