[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937673,606,1,"单选题","（2018年真题）下列任务中，属于工程项目外部管理的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可行性研究",false,{"key":16,"text":17,"correct":14},"B","设计招标",{"key":19,"text":20,"correct":14},"C","施工图设计",{"key":22,"text":23,"correct":24},"D","项目备案",true,"本题考查的是工程项目管理的含义。选项A 属于前期阶段的内部管理工作，选项B、C属于准备阶段的内部管理工作。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]