[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937634":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937634,605,2,"多选题","下列有关消火栓管道安装要求描述正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","管道穿梁及地下室剪力墙、水池等，应装设预埋金属管",true,{"key":16,"text":17,"correct":18},"B","安装顺序一般是垂直管、横管、分支管、干管、主干管",false,{"key":20,"text":21,"correct":14},"C","管道对口焊缝上不得开口焊接支管，焊口不得安装在支吊架位置上",{"key":23,"text":24,"correct":18},"D","水压强度试验的测试点应设在系统管网的最高点",{"key":26,"text":27,"correct":14},"E","管井的消防立管安装采用从下至上的安装方法","ACE","2020新教材P184 本题考查的是消火栓管道安装。B错，管道安装必须按图样设计要求的轴线位置，标高进行定位放线。安装顺序一般是主干管、干管、分支管、横管、垂直管；D错，水压强度试验的测试点应设在系统管网的最低点。",{"id":6,"name":31,"category":32,"favorite":33},"消防技术综合能力(一级、二级)","建筑工程",0]