[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937498":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937498,605,2,"多选题","下列属于给水管网的试压和冲洗要求的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","冲洗前，对管道防晃支架、支吊架等进行检查，必要时应采取加固措施",true,{"key":16,"text":17,"correct":18},"B","管网排水坡度及辅助排水设施，符合设计要求",false,{"key":20,"text":21,"correct":14},"C","管网安装完毕后，要对其进行强度试验、冲洗和严密性试验",{"key":23,"text":24,"correct":14},"D","管网冲冼宜用水进行",{"key":26,"text":27,"correct":14},"E","强度试验和严密性试验宜用水进行","ACDE","2020新教材P169 消防给水管网施工完成后，要进行试压和冲洗，要求如下: （1）管网安装完毕后，要对其进行强度试验、冲洗和严密性试验。 （ 2） 强度试验和严密性试验宜用水进行。 （3）系统试压完成后，要及时拆除所有临时盲板及试验用的管道，并与记录核对无误。 （4 ）管网冲洗在试压合格后分段进行。冲洗顺序应先室外、后室内，先地下、后地上;室 内部分的冲洗应按配水干管、配水管、配水支管的顺序进行。",{"id":6,"name":31,"category":32,"favorite":33},"消防技术综合能力(一级、二级)","建筑工程",0]