[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937494":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937494,605,2,"多选题","消防给水管网施工完成后，要进行试压和冲洗，下列管网试压和冲洗要求正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","系统试压完成后，要及时拆除所有临时盲板及试验用的管道",true,{"key":16,"text":17,"correct":18},"B","管网冲洗顺序先室内，后室外；先地上，后地下",false,{"key":20,"text":21,"correct":14},"C","管网冲洗的水流方向要与灭火时管网的水流方向一致",{"key":23,"text":24,"correct":14},"D","管网冲洗应连续进行。当出口处水的颜色、透明度与入口处水的颜色、透明度基本一致时，冲洗方可结束",{"key":26,"text":27,"correct":14},"E","管网冲洗宜设临时专用排水管道，其排放应畅通和安全。排水管道的截面面积不小于被冲洗管道截面面积的60%","ACDE","2020新教材P169 管网冲洗顺序先室外，后室内；先地下，后地上。",{"id":6,"name":31,"category":32,"favorite":33},"消防技术综合能力(一级、二级)","建筑工程",0]