[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937431":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},937431,605,1,"单选题","消防设施竣工验收不包括（ ）环节。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资料检查",false,{"key":16,"text":17,"correct":18},"B","观感质量检查",true,{"key":20,"text":21,"correct":14},"C","施工质量现场检查",{"key":23,"text":24,"correct":14},"D","质量验收判定","2020新教材P137 “消防设施施工结束后，由建设单位组织设计、施工、监理等单位进行包括消防设施在内的建设工程竣工验收。消防设施竣工验收分为资料检查、施工质量现场检查和质量验收判定三个环节，消防设施竣工验收过程中，按照各类消防设施的施工及验收规范的要求填写竣工验收记录表”，故B错误。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]