[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937427,605,1,"单选题","各类消防设施施工结束后，由施工单位或者其委托的具有调试能力的其他单位组织实施消防设施调试，其工作内容不包括（ ）。一，",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","消防设施的组件调试",false,{"key":16,"text":17,"correct":14},"B","消防设施的系统联动调试",{"key":19,"text":20,"correct":21},"C","消防设施周期性调试",true,{"key":23,"text":24,"correct":14},"D","消防设施的单机设备调试","2020新教材P135 “各类消防设施施工结束后，由施工单位或者其委托的具有调试能力的其他单位组织实施消防设施调试，调试工作包括各类消防设施的单机设备、组件调试和系统联动调试等内容”，故C错误。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]