[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937402":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937402,605,1,"单选题","消防设施施工安装以经法定机构批准或者备案的消防设计文件、国家工程建设消防技术标准为依据；经批准或者备案的消防设计文件不得擅自变更，确需变更的，由（ ）修改，报经原批准机构批准后，方可用于施工安装。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":14},"C","消防机构",{"key":22,"text":23,"correct":24},"D","原设计单位",true,"2020新教材P135 经批准或者备案的消防设计文件不得擅自变更，确需变更的，由原设计单位修改，报经原批准机构批准后，方可用于施工安装。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]