[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937053":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937053,605,1,"单选题","消防给水管网施工完成后，需要进行试压和冲洗试验。对于消防给水及消火栓系统，正确的操作顺序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管网冲洗、水压强度试验、严密性试验",false,{"key":16,"text":17,"correct":14},"B","水压强度试验、严密性试验、管网冲洗",{"key":19,"text":20,"correct":21},"C","水压强度试验、管网冲洗、严密性试验",true,{"key":23,"text":24,"correct":14},"D","管网冲洗、严密性试验、水压强度试验","参考《消防给水及消火栓系统技术规范》12.4.1：“消防给水及消火栓系统试压和冲洗应符合下列要求：1管网安装完毕后，应对其进行强度试验、冲洗和严密性试验；4.管网冲洗应在试压合格后分段进行。冲洗顺序应先室外、后室内；先地下，后地上；室内部分的冲洗应按供水干管、水平管和立管的顺序进行：”参考《消防给水及消火栓系统技术规范》12.4.4：“水压严密性试验应在水压强度试验和管网冲洗合格后进行”，故三者顺序为：强度试验（试压）→管网冲洗→严密性试验，故C正确。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]