[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937051":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937051,605,2,"多选题","消防技术服务机构对某单位的预作用自动喷水灭火系统进行竣工验收，管网部分验收记录如下，其中检查数量和检查方法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对照图纸观察检查系统中的末端试水装置、试水阀、排气阀，符合设计要求",false,{"key":16,"text":17,"correct":18},"B","抽查设计数量20%的闸阀，合格率为100%",true,{"key":20,"text":21,"correct":18},"C","抽查设计数量20%的柔性接头，合格率为100%",{"key":23,"text":24,"correct":18},"D","抽查设计数量10%的各类支架、吊架和防晃支架，合格率为100%",{"key":26,"text":27,"correct":14},"E","用秒表测量管道充水时间为1min，合格","BCD","《自动喷水灭火系统施工及验收规范》（GB 50261-2005），8.0.8，闸阀、柔性接头的抽查比例应为30%，支架等抽查比例应为20%。",{"id":6,"name":31,"category":32,"favorite":33},"消防技术综合能力(一级、二级)","建筑工程",0]