[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},936656,605,1,"单选题","下列有关施工现场临时室外消防给水系统设置要求的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","临时用房单体体积大于10000m3时，应设置 临时室外消防给水系统",true,{"key":16,"text":17,"correct":18},"B","临时用房的建筑面积之和为6000㎡时，其火灾延续时间可为1．0h",false,{"key":20,"text":21,"correct":18},"C","在建工程的体积大于30000m3时，其火灾延续时间不应小于2．0h",{"key":23,"text":24,"correct":18},"D","施工现场临时室外消防给水系统给水管网宜布置成环状","根据《建设工程施工现场消防安全技术规范》GB 50720—20115．3．4，临时用房建筑面积之和大于1000㎡或在建工程单体体积大于10000m3时，应设置临时室外消防给水系统，要注意临时用房和在建工程的不同，A选项错误；根据5．3．5表，B选项正确；根据表5．3．6，在建工程的体积大于30000m3时应不应低于2．0h，C选项正确；5．3．7—1，施工现场临时室外消防给水系统给水管网宜布置成环状，D选项正确。本题答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]