[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},936638,605,1,"单选题","下列临时用房的防火设计，符合规范要求的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","厨房操作间与宿舍组合建造的临时用房",false,{"key":16,"text":17,"correct":14},"B","办公用房与锅炉房组合建造的临时用房",{"key":19,"text":20,"correct":14},"C","某临时用房第二层设为员工棋牌室",{"key":22,"text":23,"correct":24},"D","某临时用房首层为会议室",true,"根据《建设工程施工现场消防安全技术规范》GB 50720—20114．2．3，其他防火设计应符合下列规定： 1）宿舍、办公用房不应与厨房操作间、锅炉房、变配电房等组合建造。 2）会议室、文化娱乐室等人员密集的房间应设置在临时用房的第一层，其疏散门应向疏散方向开启。 本题答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]