[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936481":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},936481,605,1,"单选题","城市消防远程监控系统正式投入使用前，对系统及系统组件进行调试。系统在各项功能调试后进行试运行，试运行时间不少于（ ）月。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1个",true,{"key":16,"text":17,"correct":18},"B","2个",false,{"key":20,"text":21,"correct":18},"C","3个",{"key":23,"text":24,"correct":18},"D","4个","城市消防远程监控系统正式投入使用前，对系统及系统组件进行调试。系统在各项功能调试后进行试运行，试运行时间不少于1个月。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]