[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},936303,605,1,"单选题","下列不属于防排烟系统中活动挡烟垂壁的调试的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","手动操作挡烟垂壁按钮进行开启、复位试验，挡烟垂壁应灵敏、可靠地启动与到位后停止，下降高度符合设计要求",false,{"key":16,"text":17,"correct":14},"B","模拟火灾，相应区域火灾报警后，同一防烟区域内挡烟垂壁应联动下降到设计高度",{"key":19,"text":20,"correct":21},"C","活动挡烟垂壁关闭后应能联动相应的风机停止",true,{"key":23,"text":24,"correct":14},"D","挡烟垂壁下降到设计高度后应能将状态信号反馈到消防控制室","防排烟系统中，活动挡烟垂壁的调试包括： （1）手动操作挡烟垂壁按钮进行开启、复位试验，挡烟垂壁应灵敏、可靠地启动与到位后停止，下降高度符合设计要求。 （2）模拟火灾，相应区域火灾报警后，同一防烟区域内挡烟垂壁应联动下降到设计高度。 （3）挡烟垂壁下降到设计高度后应能将状态信号反馈到消防控制室。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]