[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936218":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},936218,605,2,"多选题","干粉灭火系统系统试压试验和管网吹扫在管网安装完毕后进行，下列规定试压、吹扫条件符合要求的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","经复查，埋地管道的位置及管道基础、支墩等符合设计文件要求",true,{"key":16,"text":17,"correct":18},"B","准备不少于2只的试压用压力表，精度不低于2．0级，量程为试验压力值的1．5～2．0倍",false,{"key":20,"text":21,"correct":14},"C","加设的1临时盲板具有突出于法兰的边耳，且有明显标志，并对临时盲板数量、位置进行记录",{"key":23,"text":24,"correct":14},"D","隔离或者拆除不能参与试压的设备、仪表、阀门及附件",{"key":26,"text":27,"correct":14},"E","采用生活用水进行水压试验和管网冲洗，不得使用海水或者含有腐蚀性化学物质的水进行试压试验、管网冲洗","ACDE","准备不少于2只的试压用压力表，精度不低于1．5级，量程为试验压力值的1．5～2．0倍。",{"id":6,"name":31,"category":32,"favorite":33},"消防技术综合能力(一级、二级)","建筑工程",0]