[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},936163,605,1,"单选题","根据《泡沫灭火系统施工及验收规范》GB 50281—2006规定，在系统调试时，泡沫灭火系统的动力源和备用动力应进行切换试验，动力源和备用动力及电气设备运行应正常，当为自动控制方式时，最少应进行（ ）次试验。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","5","根据《泡沫灭火系统施工及验收规范》GB 50281—20066．2．1，泡沫灭火系统的动力源和备用动力应进行切换试验，动力源和备用动力及电气设备运行应正常。 检查数量：全数检查。检查方法：当为手动控制时，以手动的方式进行1—2次试验；当为自动控制时，以自动和手动的方式各进行1—2次试验。本题答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]