[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936125":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},936125,605,1,"单选题","气体灭火系统的调试应在系统安装完毕，并宜在相关的火灾报警系统和开口自动关闭装置、通风机械和防火阀等联动设备的调试完成后进行，调试的项目不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","模拟启动试验",false,{"key":16,"text":17,"correct":14},"B","模拟喷气试验",{"key":19,"text":20,"correct":21},"C","模拟泄放试验",true,{"key":23,"text":24,"correct":14},"D","模拟切换操作试验","《气体灭火系统施工及验收规范》（GB．50263-2007），6.1.5，调试项目应包括模拟启动试验、模拟喷气试验和模拟切换操作试验，并应按本规范表C-4填写施工过程检查记录。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]