[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936033":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},936033,605,1,"单选题","某自动喷水灭火系统安装工地到新到场的末端试水装置进行进场检验。根据现行规范要求，末端试水装置密封性能试验的压力和保压时间分别是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","额定工作压力的1.1倍和5min",true,{"key":16,"text":17,"correct":18},"B","额定工作压力的1.2倍和5min",false,{"key":20,"text":21,"correct":18},"C","额定工作压力的1.1倍和3min",{"key":23,"text":24,"correct":18},"D","额定工作压力的1.2倍和3min","测试末端试水装置密封性能，试验压力为额定工作压力的1.1倍，保压时间为5min，末端试水装置试水阀关闭，测试结束时末端试水装置各组件无渗漏。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]