[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-936019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},936019,605,1,"单选题","下列关于末端试水装置的密封性能检查中，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","试验压力应为额定工作压力1．5倍的静水压力，保压时间应不小于2min",false,{"key":16,"text":17,"correct":18},"B","试验压力应为额定工作压力1．1倍的静水压力，保压时间应不小于5min",true,{"key":20,"text":21,"correct":14},"C","试验压力应为额定工作压力1．5倍的静水压力，保压时间应不小于5min",{"key":23,"text":24,"correct":14},"D","试验压力应为额定工作压力1．1倍的静水压力，保压时间应不小于2min","根据《自动喷水灭火系统第21部分：末端试水装置》GB 5135．21—20117．4，将末端试水装置安装在试验装置上，冲水排除空气后，对试件缓慢升压至1．1倍额定工作压力，保持5min，试验中末端试水装置的试水阀门处于关闭状态。本题答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]