[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-935908":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},935908,605,1,"单选题","下列关于室内消火栓系统管网试压和冲洗的顺序，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","严密性试验—强度试验—冲洗",false,{"key":16,"text":17,"correct":14},"B","冲洗—强度试验—严密性试验",{"key":19,"text":20,"correct":21},"C","强度试验—冲洗—严密性试验",true,{"key":23,"text":24,"correct":14},"D","强度试验—严密性试验—冲洗","根据《消防给水及消火栓系统技术规范》GB 50974—201412．4．1，管网安装完毕后，应对其进行强度试验、冲洗和严密性试验。本题答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]