[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-935854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},935854,605,1,"单选题","根据《消防给水及消火栓系统技术规范》（GB50974—2014）的规定，室内消火栓系统管网安装完成后，对其进行水压试验和冲洗的正确顺序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","强度试验—严密性试验—冲洗",false,{"key":16,"text":17,"correct":18},"B","强度试验—冲洗—严密性试验",true,{"key":20,"text":21,"correct":14},"C","冲洗—强度试验—严密性试验",{"key":23,"text":24,"correct":14},"D","冲洗—严密性试验—强度试验","《消防给水及消火栓系统技术规范》（GB50974—2014）第12．4．1．1条规定，消防给水及消火栓系统管网安装完毕后，应对其进行强度试验、冲洗和严密性试验。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]