[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-935409":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},935409,605,1,"单选题","城市消防站的布置应结合城市交通状况和各区域的火灾危险性进行合理布局；街区道路布置和市政消火栓的布局应能满足灭火救援的需要，街区道路中心线间距离一般在（ ）m以内，市政消火栓沿可通行消防车的街区道路布置，间距不得大于（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","150，110",false,{"key":16,"text":17,"correct":18},"B","160，120",true,{"key":20,"text":21,"correct":14},"C","150，120",{"key":23,"text":24,"correct":14},"D","160，110","城市消防站的布置结合城市交通状况和各区域的火灾危险性进行合理布局；街区道路布置和市政消火栓的布局能满足灭火救援需要，街区道路中心线间距离一般在160m以内，市政消火栓沿可通行消防车的街区道路布置，间距不得大于120m。因此，本题的正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]