[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-935245":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},935245,605,1,"单选题","(2017年真题) 某在建工程，单体体积为35000m3，设计建筑高度为23.5m，临时用房建筑面积为1200㎡，设置了临时室内、外消防给水系统。该建筑工程施工现场临时消防设施设置的做法中，不符合现行国家消防技术标准要求的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","临时室外消防给水干管的管径采用DN100",false,{"key":16,"text":17,"correct":14},"B","设置了两根室内临时消防竖管",{"key":19,"text":20,"correct":14},"C","每个室内消火栓处只设置接口，未设置消防水带和消防水枪",{"key":22,"text":23,"correct":24},"D","在建工程临时室外消防用水量按火灾延续时间1.00h确定",true,"在建工程临时室外消防用水量。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]