[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-935050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},935050,605,1,"单选题","(2016年真题)消防检测机构对某单位安装的干粉预制灭火装置进行检测，下列检测结果中，不符合现行国家消防技术标准规定的是（??）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管道长度为18m",false,{"key":16,"text":17,"correct":18},"B","灭火剂储存量为160KG",true,{"key":20,"text":21,"correct":14},"C","工作压力2.3MPa",{"key":23,"text":24,"correct":14},"D","一个防护区使用3套预制灭火装置","根据《气体灭火系统设计规范》(GB 50370—2005)第3．4．1条，干粉预制灭火装置符合： 1、灭火剂储存量不得大于150Kg; 2、管道长度不得大于20M 3、工作压力不得大于2.5MPa; 4、一个防护区或保护对象所用预制灭火剂装置最多不超过4套，并且同时启动，其动作响应时间差不得大于2S。",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]