[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-934997":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},934997,605,1,"单选题","(2015年真题) 自动喷水灭火系统水流指示器的安装应在管道试压和冲洗合格后进行，在水流指示器前管道上安装的信号阀，与水流指示器之间的距离不宜小于（）mm。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","400",false,{"key":16,"text":17,"correct":14},"B","500",{"key":19,"text":20,"correct":21},"C","300",true,{"key":23,"text":24,"correct":14},"D","600","自动喷水灭火系统水流指示器的安装应该在管道试压和冲洗合格后进行，在水流指示器前管道上安装的信号阀，与水流指示器之间的距离不宜小于300mm",{"id":6,"name":27,"category":28,"favorite":29},"消防技术综合能力(一级、二级)","建筑工程",0]