[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-933164":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},933164,604,1,"单选题","某火力发电厂输煤栈桥输送皮带总长550m，采用水喷雾灭火系统保护时，该输煤栈桥最多可划分为（ ）段分段进行保护。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","6",{"key":23,"text":24,"correct":14},"D","7","根据《水喷雾灭火系统技术规范》（GB50219—2014）第3．1．6条规定，输送机皮带的保护面积应按上行皮带的上表面面积确定；长距离的皮带宜实施分段保护。但每段长度不宜小于100m。本题中输煤栈桥输送皮带总长550m，实施分段保护，每段长度不宜小于100m，最多可划分为5段分段进行保护。",{"id":6,"name":27,"category":28,"favorite":29},"消防安全技术实务(一级)","建筑工程",0]