[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931942":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931942,604,2,"多选题","（2020年真题）关于加压送风系统控制的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","加压送风机应能现场手动启动",true,{"key":16,"text":17,"correct":14},"B","加压送风机应能通过火灾自动报警系统自动启动",{"key":19,"text":20,"correct":14},"C","加压送风机应能在消防控制室手动启动",{"key":22,"text":23,"correct":24},"D","防火分区内确认火灾后，应能在20s内联动开启加压送风机",false,{"key":26,"text":27,"correct":14},"E","系统中任一常闭加压送风口开启时，加压风机应能自动启动","ABCE","P488-495 加压送风机的启动应符合下列规定： ①现场手动启动 ②通过火灾自动报警系统自动启动 ③消防控制室手动启动 ④系统中任一常闭加压送风口开启时，加压风机应能自动启动。 联动控制：加压送风口所在防火分区内的两只独立的火灾探测器或一只探测器与一只手动火灾报警按钮的报警信号，联动开启送风口，启动加压送风机。 当防火分区内火灾确认后，应能在15S内联动开启常闭加压送风口和加压送风机。并应符合下列规定： ①应开启该防火分区楼梯间的全部加压风机； ②应开启该防火分区内着火层及其相邻上下层前室及合用前室的常闭加压送风口，同时开启加压送风机。",{"id":6,"name":31,"category":32,"favorite":33},"消防安全技术实务(一级)","建筑工程",0]