[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-603-1":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":671},{"id":5,"name":6,"category":7,"favorite":8},603,"质量、投资、进度控制","建筑工程",0,1,50,656,[13,33,50,60,75,87,102,114,129,141,156,168,183,195,210,222,237,249,263,275,290,302,317,329,343,351,365,377,391,403,417,429,443,455,464,476,490,502,516,531,543,557,569,584,596,609,621,635,647,661],{"id":14,"libraryId":5,"type":9,"typeLabel":15,"stem":16,"options":17,"answer":23,"analysis":32},931020,"单选题","某双代号网络计划，已知工作K的持续时间为7天，最迟完成时间为第30天。工作K有三项紧前工作，它们的最早完成时间分别是第13天、第15天和第17天，则工作K的总时差为( )天。",[18,22,26,29],{"key":19,"text":20,"correct":21},"A","4",false,{"key":23,"text":24,"correct":25},"B","6",true,{"key":27,"text":28,"correct":21},"C","8",{"key":30,"text":31,"correct":21},"D","10","",{"id":34,"libraryId":5,"type":35,"typeLabel":36,"stem":32,"options":37,"answer":49,"analysis":32},931021,2,"多选题",[38,40,42,44,46],{"key":19,"text":39,"correct":25},"第2周期间实际完成任务量超过计划2%",{"key":23,"text":41,"correct":21},"该设备焊接过程未按原计划开始",{"key":27,"text":43,"correct":25},"到第3周末该过程实际累计完成任务量与计划进度一致",{"key":30,"text":45,"correct":25},"第4周该设备焊接过程出现停工",{"key":47,"text":48,"correct":21},"E","该设备焊接过程按计划完成","ACD",{"id":51,"libraryId":5,"type":9,"typeLabel":15,"stem":52,"options":53,"answer":19,"analysis":32},931022,"某工程网络计划中，工作A的最早开始时间为第20天，持续时间为7天，该工作有三项紧后工作，它们的最迟开始时间分别为第43天、第30天和第33天，则工作A的总时差为( )天。",[54,56,57,58],{"key":19,"text":55,"correct":25},"3",{"key":23,"text":24,"correct":21},{"key":27,"text":31,"correct":21},{"key":30,"text":59,"correct":21},"16",{"id":61,"libraryId":5,"type":35,"typeLabel":36,"stem":62,"options":63,"answer":74,"analysis":32},931023,"在工程建设施工阶段，当通过压缩网络计划中关键工作的持续时间来缩短工期时，通常采取的技术措施有( )。",[64,66,68,70,72],{"key":19,"text":65,"correct":25},"采用更先进的施工方法",{"key":23,"text":67,"correct":21},"增加劳动力和施工机械的数量",{"key":27,"text":69,"correct":25},"改进施工工艺和施工技术",{"key":30,"text":71,"correct":21},"改善劳动条件",{"key":47,"text":73,"correct":25},"采用更先进的施工机械","ACE",{"id":76,"libraryId":5,"type":9,"typeLabel":15,"stem":77,"options":78,"answer":30,"analysis":32},931024,"下列方法中，可用于价值工程对象选择的是( )。",[79,81,83,85],{"key":19,"text":80,"correct":21},"成本分析法",{"key":23,"text":82,"correct":21},"功能分析法",{"key":27,"text":84,"correct":21},"德尔菲法",{"key":30,"text":86,"correct":25},"ABC分析法",{"id":88,"libraryId":5,"type":35,"typeLabel":36,"stem":89,"options":90,"answer":101,"analysis":32},931025,"下列项目风险防范对策中，属于风险转移的是( )。",[91,93,95,97,99],{"key":19,"text":92,"correct":25},"向保险公司投保",{"key":23,"text":94,"correct":25},"通过分包，将部分风险转移给承包商",{"key":27,"text":96,"correct":21},"改变项目方案",{"key":30,"text":98,"correct":21},"与其他企业合作",{"key":47,"text":100,"correct":21},"做好处理风险的准备工作","AB",{"id":103,"libraryId":5,"type":9,"typeLabel":15,"stem":104,"options":105,"answer":23,"analysis":32},931026,"过程能力是指产品生产的每个过程对产品质量的保证程度，其高低可以用标准差σ的大小来衡量，下列说法正确的是( )。",[106,108,110,112],{"key":19,"text":107,"correct":21},"过程能力越强、σ越小，则过程越不稳定",{"key":23,"text":109,"correct":25},"过程能力越弱、σ越大，则过程越不稳定",{"key":27,"text":111,"correct":21},"过程能力与σ无关，与产品的技术要求有关",{"key":30,"text":113,"correct":21},"σ既取决于质量因素，又与规范有关",{"id":115,"libraryId":5,"type":35,"typeLabel":36,"stem":116,"options":117,"answer":128,"analysis":32},931027,"市场要求是构成质量屋的主要部分之一，通常是指顾客要求和社会要求，这些要求应包括( )方面的内容。",[118,120,122,124,126],{"key":19,"text":119,"correct":25},"产品质量",{"key":23,"text":121,"correct":25},"产品成本",{"key":27,"text":123,"correct":21},"产品数量",{"key":30,"text":125,"correct":25},"上市时间",{"key":47,"text":127,"correct":25},"服务和环境","ABDE",{"id":130,"libraryId":5,"type":9,"typeLabel":15,"stem":131,"options":132,"answer":27,"analysis":32},931028,"当采用匀速进展横道图比较法时，如果表示实际进度的横道线右端点位于检查日期的右侧，则该端点与检查日期的距离表示工作( )。",[133,135,137,139],{"key":19,"text":134,"correct":21},"实际少消耗的时间",{"key":23,"text":136,"correct":21},"实际多消耗的时间",{"key":27,"text":138,"correct":25},"进度超前的时间",{"key":30,"text":140,"correct":21},"进度拖后的时间",{"id":142,"libraryId":5,"type":35,"typeLabel":36,"stem":143,"options":144,"answer":155,"analysis":32},931029,"审查施工组织设计是施工准备阶段监理工程师进行质量控制的重要工作，这项工作的内容应包括( )。",[145,147,149,151,153],{"key":19,"text":146,"correct":25},"对承包单位编制的施工组织设计的审核签认由总监负责",{"key":23,"text":148,"correct":21},"承包商应按审定的施工组织设计文件组织施工，不得对其进行调整",{"key":27,"text":150,"correct":21},"经审定的施工组织设计应由项目监理机构报送工程质量监督机构",{"key":30,"text":152,"correct":25},"经审定的施工组织设计应由项目监理机构报送建设单位",{"key":47,"text":154,"correct":25},"经建设单位批准，工艺复杂的工程可分阶段报审施工组织设计","ADE",{"id":157,"libraryId":5,"type":9,"typeLabel":15,"stem":158,"options":159,"answer":27,"analysis":32},931030,"当工程网络计划的计算工期不等于计划工期时，正确的结论是( )。",[160,162,164,166],{"key":19,"text":161,"correct":21},"关键节点最早时间等于最迟时间",{"key":23,"text":163,"correct":21},"关键工作的自由时差为零",{"key":27,"text":165,"correct":25},"关键线路上相邻工作的时间间隔为零",{"key":30,"text":167,"correct":21},"关键工作最早开始时间等于最迟开始时间",{"id":169,"libraryId":5,"type":35,"typeLabel":36,"stem":170,"options":171,"answer":182,"analysis":32},931031,"对策表的应用过程包括( )。",[172,174,176,178,180],{"key":19,"text":173,"correct":21},"对策措施",{"key":23,"text":175,"correct":25},"为工序编号。",{"key":27,"text":177,"correct":25},"确定存在问题。",{"key":30,"text":179,"correct":25},"确定对策。",{"key":47,"text":181,"correct":25},"确定每种对策的负责人、完成日期","BCDE",{"id":184,"libraryId":5,"type":9,"typeLabel":15,"stem":185,"options":186,"answer":23,"analysis":32},931032,"产品认证是评定产品本身满足标准规范的符合性。下列选项中，属于产品认证的是( )。",[187,189,191,193],{"key":19,"text":188,"correct":21},"质量管理体系认证",{"key":23,"text":190,"correct":25},"3C认证",{"key":27,"text":192,"correct":21},"环境管理体系认证",{"key":30,"text":194,"correct":21},"职业健康安全管理体系认证",{"id":196,"libraryId":5,"type":35,"typeLabel":36,"stem":197,"options":198,"answer":209,"analysis":32},931033,"下列关于现金流量图的说法，正确的有( )。",[199,201,203,205,207],{"key":19,"text":200,"correct":21},"现金流量图反映的是投资活动资金运动状态",{"key":23,"text":202,"correct":25},"横轴表示时间轴",{"key":27,"text":204,"correct":25},"与横轴垂直向下的箭头代表现金流出",{"key":30,"text":206,"correct":25},"与横轴垂直向上的箭头代表现金流入",{"key":47,"text":208,"correct":21},"现金流量图的时间单位必须是年","BCD",{"id":211,"libraryId":5,"type":9,"typeLabel":15,"stem":212,"options":213,"answer":19,"analysis":32},931034,"“按图检验”不可行的原因不包括( )。",[214,216,218,220],{"key":19,"text":215,"correct":25},"可进行全数检验",{"key":23,"text":217,"correct":21},"图样中并未规定抽样方案，",{"key":27,"text":219,"correct":21},"图样上未规定不合格的判定规则",{"key":30,"text":221,"correct":21},"图样中规定的某些尺寸既无必要进行检验，也难以检验",{"id":223,"libraryId":5,"type":35,"typeLabel":36,"stem":224,"options":225,"answer":236,"analysis":32},931035,"建设工程静态投资包括( )。",[226,228,230,232,234],{"key":19,"text":227,"correct":25},"建筑安装工程费",{"key":23,"text":229,"correct":25},"设备工器具购置费",{"key":27,"text":231,"correct":25},"工程建设其他费",{"key":30,"text":233,"correct":25},"基本预备费",{"key":47,"text":235,"correct":21},"土地使用税","ABCD",{"id":238,"libraryId":5,"type":9,"typeLabel":15,"stem":239,"options":240,"answer":19,"analysis":32},931036,"失效模式及影响分析的流程步骤中，首要步骤是( )。",[241,243,245,247],{"key":19,"text":242,"correct":25},"描述产品或过程",{"key":23,"text":244,"correct":21},"定义功能",{"key":27,"text":246,"correct":21},"识别潜在失效",{"key":30,"text":248,"correct":21},"确定原因并归类",{"id":250,"libraryId":5,"type":35,"typeLabel":36,"stem":32,"options":251,"answer":262,"analysis":32},931037,[252,254,256,258,260],{"key":19,"text":253,"correct":21},"在第5周末工作C进度尚有总时差1周",{"key":23,"text":255,"correct":25},"在第5周末工作E进度拖后且影响工期1周",{"key":27,"text":257,"correct":21},"在第9周末整体工程进度拖后1周",{"key":30,"text":259,"correct":21},"在第9周末工作F尚有时差2周",{"key":47,"text":261,"correct":25},"在第9周末工作H进度拖后，影响工作1周","BE",{"id":264,"libraryId":5,"type":9,"typeLabel":15,"stem":265,"options":266,"answer":30,"analysis":32},931038,"下列选项中，不属于FMEA方法特点的是( )。",[267,269,271,273],{"key":19,"text":268,"correct":21},"规范化",{"key":23,"text":270,"correct":21},"标准化",{"key":27,"text":272,"correct":21},"系统化",{"key":30,"text":274,"correct":25},"集成化",{"id":276,"libraryId":5,"type":35,"typeLabel":36,"stem":277,"options":278,"answer":289,"analysis":32},931039,"设备设计过程质量监理的依据包括( )。",[279,281,283,285,287],{"key":19,"text":280,"correct":25},"有关设备工程建设和质量管理的法律法规",{"key":23,"text":282,"correct":25},"项目的可行性研究与评估报告",{"key":27,"text":284,"correct":25},"设计纲要与合同",{"key":30,"text":286,"correct":21},"设计图纸和技术说明书",{"key":47,"text":288,"correct":25},"设计技术标准","ABCE",{"id":291,"libraryId":5,"type":9,"typeLabel":15,"stem":292,"options":293,"answer":23,"analysis":32},931040,"12%人可向甲、乙两家银行申请贷款，到期一次性偿还本息。甲银行贷款年利率12%，每季度计息一次；乙银行贷款年利率13%，每半年计息一次。借款人按利率高低作出正确选择后，其借款年实际利率为( )。",[294,296,298,300],{"key":19,"text":295,"correct":21},"12%",{"key":23,"text":297,"correct":25},"12.55%",{"key":27,"text":299,"correct":21},"13%",{"key":30,"text":301,"correct":21},"13.42%",{"id":303,"libraryId":5,"type":35,"typeLabel":36,"stem":304,"options":305,"answer":316,"analysis":32},931041,"寿命期不等的互斥方案比选可以采用的方法有( )。",[306,308,310,312,314],{"key":19,"text":307,"correct":21},"价值工程法",{"key":23,"text":309,"correct":21},"挣值分析法",{"key":27,"text":311,"correct":25},"净年值法",{"key":30,"text":313,"correct":21},"内部收益率法",{"key":47,"text":315,"correct":25},"费用年值法","CE",{"id":318,"libraryId":5,"type":9,"typeLabel":15,"stem":319,"options":320,"answer":27,"analysis":32},931042,"财务净现值为零，表明项目盈利能力水平( )。",[321,323,325,327],{"key":19,"text":322,"correct":21},"大于基准收益率",{"key":23,"text":324,"correct":21},"小于基准收益率",{"key":27,"text":326,"correct":25},"等于基准收益率",{"key":30,"text":328,"correct":21},"等于零",{"id":330,"libraryId":5,"type":35,"typeLabel":36,"stem":331,"options":332,"answer":289,"analysis":32},931043,"安装工程定额包括( )定额。",[333,335,337,339,341],{"key":19,"text":334,"correct":25},"机械设备安装",{"key":23,"text":336,"correct":25},"电气设备安装",{"key":27,"text":338,"correct":25},"自动化仪表安装",{"key":30,"text":340,"correct":21},"电气照明安装",{"key":47,"text":342,"correct":25},"静置设备与工艺金属结构安装",{"id":344,"libraryId":5,"type":9,"typeLabel":15,"stem":345,"options":346,"answer":23,"analysis":32},931044,"在过程能力评价中，按照过程能力分级表判定，当过程能力指数( )时，表明过程能力正常。",[347,348,349,350],{"key":19,"text":32,"correct":21},{"key":23,"text":32,"correct":25},{"key":27,"text":32,"correct":21},{"key":30,"text":32,"correct":21},{"id":352,"libraryId":5,"type":35,"typeLabel":36,"stem":353,"options":354,"answer":236,"analysis":32},931045,"规范故障树(FT A)是指仅包括( )逻辑门的故障树。",[355,357,359,361,363],{"key":19,"text":356,"correct":25},"底事件",{"key":23,"text":358,"correct":25},"结果事件",{"key":27,"text":360,"correct":25},"与门、或门",{"key":30,"text":362,"correct":25},"非门",{"key":47,"text":364,"correct":21},"意外事件",{"id":366,"libraryId":5,"type":9,"typeLabel":15,"stem":367,"options":368,"answer":23,"analysis":32},931046,"监理工程师按委托监理合同要求对设计工作进度进行监控时，其主要工作内容有( )。",[369,371,373,375],{"key":19,"text":370,"correct":21},"编制阶段性设计进度计划",{"key":23,"text":372,"correct":25},"定期检查设计工作实际进展情况",{"key":27,"text":374,"correct":21},"协调设计各专业之间的配合关系",{"key":30,"text":376,"correct":21},"建立健全设计技术经济定额",{"id":378,"libraryId":5,"type":35,"typeLabel":36,"stem":379,"options":380,"answer":128,"analysis":32},931047,"由于业主原因，工程暂停一个月，则承包商可索赔( )。",[381,383,385,387,389],{"key":19,"text":382,"correct":25},"材料超期储存费用",{"key":23,"text":384,"correct":25},"施工机械窝工费",{"key":27,"text":386,"correct":21},"合理的利润",{"key":30,"text":388,"correct":25},"工人窝工费",{"key":47,"text":390,"correct":25},"增加的利息支出",{"id":392,"libraryId":5,"type":9,"typeLabel":15,"stem":393,"options":394,"answer":23,"analysis":32},931048,"承接工程设计任务时，( )工程设计行业资质单位承担相应行业中、小型建设项目的工程设计任务，地区不受限制。",[395,397,399,401],{"key":19,"text":396,"correct":21},"甲级",{"key":23,"text":398,"correct":25},"乙级",{"key":27,"text":400,"correct":21},"丙级",{"key":30,"text":402,"correct":21},"丁级",{"id":404,"libraryId":5,"type":35,"typeLabel":36,"stem":405,"options":406,"answer":101,"analysis":32},931049,"下列项目财务评价指标中，属于静态指标的是( )。",[407,409,411,413,415],{"key":19,"text":408,"correct":25},"总投资收益率",{"key":23,"text":410,"correct":25},"项目资本金净利润率",{"key":27,"text":412,"correct":21},"净年值",{"key":30,"text":414,"correct":21},"净年值率",{"key":47,"text":416,"correct":21},"内部收益率",{"id":418,"libraryId":5,"type":9,"typeLabel":15,"stem":419,"options":420,"answer":23,"analysis":32},931050,"狭义的质量功能展开就是把形成质量的( )，按目的手段系列中的步骤进行详细的展开。",[421,423,425,427],{"key":19,"text":422,"correct":21},"功能及目标",{"key":23,"text":424,"correct":25},"职能及业务",{"key":27,"text":426,"correct":21},"方法及手段",{"key":30,"text":428,"correct":21},"成本及途径",{"id":430,"libraryId":5,"type":35,"typeLabel":36,"stem":431,"options":432,"answer":182,"analysis":32},931051,"下列关于净年值的说法，正确的有( )。",[433,435,437,439,441],{"key":19,"text":434,"correct":21},"可以直接用于有资金约束条件下的独立方案选择",{"key":23,"text":436,"correct":25},"可以用于寿命期不等的互斥方案比选",{"key":27,"text":438,"correct":25},"可以说明某项目单位投资现值所能实现的净现值大小",{"key":30,"text":440,"correct":25},"若某项目的净现值大于零，则其净年值也会大于零",{"key":47,"text":442,"correct":25},"对两个寿命期相等的互斥项目进行比选时，应选择净年值较大的项目",{"id":444,"libraryId":5,"type":9,"typeLabel":15,"stem":445,"options":446,"answer":23,"analysis":32},931052,"建立故障树时，在确定顶事件之前，应该做的工作是( )。",[447,449,451,453],{"key":19,"text":448,"correct":21},"定量计算",{"key":23,"text":450,"correct":25},"故障因果关系分析",{"key":27,"text":452,"correct":21},"简化系统",{"key":30,"text":454,"correct":21},"自上而下逐级建立故障树",{"id":456,"libraryId":5,"type":35,"typeLabel":36,"stem":32,"options":457,"answer":463,"analysis":32},931053,[458,459,460,461,462],{"key":19,"text":32,"correct":25},{"key":23,"text":32,"correct":25},{"key":27,"text":32,"correct":21},{"key":30,"text":32,"correct":21},{"key":47,"text":32,"correct":25},"ABE",{"id":465,"libraryId":5,"type":9,"typeLabel":15,"stem":466,"options":467,"answer":30,"analysis":32},931054,"在工程网络计划执行中，如果某项工作进度拖延的时间超过了该项工作的总时差，在确定进度计划的调整方法时，则需要考虑( )的限制条件。",[468,470,472,474],{"key":19,"text":469,"correct":21},"后续工作最早开始时间",{"key":23,"text":471,"correct":21},"关键节点的最早时间",{"key":27,"text":473,"correct":21},"紧后工作最早开始时间",{"key":30,"text":475,"correct":25},"后续工作和总工期",{"id":477,"libraryId":5,"type":35,"typeLabel":36,"stem":32,"options":478,"answer":489,"analysis":32},931055,[479,481,483,485,487],{"key":19,"text":480,"correct":25},"关键线路有2条",{"key":23,"text":482,"correct":25},"工作1～3与工作3～6的总时差相等",{"key":27,"text":484,"correct":21},"工作4～7与工作5～7的自由时差相等",{"key":30,"text":486,"correct":25},"工作2～6的总时差与自由时差相等",{"key":47,"text":488,"correct":21},"工作3～6的总时差与自由时差不等","ABD",{"id":491,"libraryId":5,"type":9,"typeLabel":15,"stem":492,"options":493,"answer":27,"analysis":32},931056,"下列关于净现值的说法，正确的是( )。",[494,496,498,500],{"key":19,"text":495,"correct":21},"若项目的净现值小于零，则项目生产期利润肯定小于零",{"key":23,"text":497,"correct":21},"若项目的净现值大于零，则投资回收期肯定大于基准投资回收期",{"key":27,"text":499,"correct":25},"若项目的净现值大于零，则净年值也肯定大于零",{"key":30,"text":501,"correct":21},"若项目的净现值等于零，则项目生产期利润肯定等于零",{"id":503,"libraryId":5,"type":35,"typeLabel":36,"stem":504,"options":505,"answer":236,"analysis":32},931057,"以下属于建设工程总概算中工程建设其他费用的是( )。",[506,508,510,512,514],{"key":19,"text":507,"correct":25},"土地使用费",{"key":23,"text":509,"correct":25},"勘察设计费",{"key":27,"text":511,"correct":25},"生产准备费",{"key":30,"text":513,"correct":25},"工程监理费",{"key":47,"text":515,"correct":21},"场外工程项目综合概算",{"id":517,"libraryId":5,"type":35,"typeLabel":36,"stem":518,"options":519,"answer":530,"analysis":32},931058,"与工程网络计划方法相比，横道图进度计划方法的优点是( )。",[520,522,524,526,528],{"key":19,"text":521,"correct":21},"适用于手工编制计划",{"key":23,"text":523,"correct":21},"适应大的进度计划系统",{"key":27,"text":525,"correct":25},"便于项目进展状况的检查",{"key":30,"text":527,"correct":25},"便于统计完成计划所需资源的时间分布",{"key":47,"text":529,"correct":21},"清楚地显示各工作之间相互联系和制约的关系","CD",{"id":532,"libraryId":5,"type":9,"typeLabel":15,"stem":533,"options":534,"answer":30,"analysis":32},931059,"建设工程组织流水施工时，相邻专业工作队之间的流水步距不尽相等，但专业工作队数等于施工过程数的流水施工方式是( )。",[535,537,539,541],{"key":19,"text":536,"correct":21},"固定节拍流水施工和加快的成倍节拍流水施工",{"key":23,"text":538,"correct":21},"加快的成倍节拍流水施工和非节奏流水施工",{"key":27,"text":540,"correct":21},"固定节拍流水施工和一般的成倍节拍流水施工",{"key":30,"text":542,"correct":25},"一般的成倍节拍流水施工和非节奏流水施工",{"id":544,"libraryId":5,"type":35,"typeLabel":36,"stem":545,"options":546,"answer":49,"analysis":32},931060,"在设备安装调试验收过程中，监理单位应( )。",[547,549,551,553,555],{"key":19,"text":548,"correct":25},"对验收资料及实物进行检查",{"key":23,"text":550,"correct":21},"按设备制造厂认可的试验大纲的规定进行试验",{"key":27,"text":552,"correct":25},"在验收移交前，督促承包商清理现场",{"key":30,"text":554,"correct":25},"认真审核并签署各种监理工作报告文件",{"key":47,"text":556,"correct":21},"检查随机文件是否齐全",{"id":558,"libraryId":5,"type":9,"typeLabel":15,"stem":559,"options":560,"answer":19,"analysis":32},931061,"质量管理体系认证始于( )。",[561,563,565,567],{"key":19,"text":562,"correct":25},"机电产品",{"key":23,"text":564,"correct":21},"建筑行业",{"key":27,"text":566,"correct":21},"服务产品",{"key":30,"text":568,"correct":21},"食品",{"id":570,"libraryId":5,"type":35,"typeLabel":36,"stem":571,"options":572,"answer":583,"analysis":32},931062,"产品认证分为( )。",[573,575,577,579,581],{"key":19,"text":574,"correct":25},"自愿性认证",{"key":23,"text":576,"correct":21},"主动性认证",{"key":27,"text":578,"correct":25},"强制性认证",{"key":30,"text":580,"correct":21},"被动性认证",{"key":47,"text":582,"correct":21},"外部认证","AC",{"id":585,"libraryId":5,"type":9,"typeLabel":15,"stem":586,"options":587,"answer":19,"analysis":32},931063,"在项目财务分析中，可判定项目可行的是( )。",[588,590,592,594],{"key":19,"text":589,"correct":25},"静态投资回收期小于行业标准投资回收期",{"key":23,"text":591,"correct":21},"财务内部收益率小于基准收益率",{"key":27,"text":593,"correct":21},"总投资收益率低于同行业收益率参考值",{"key":30,"text":595,"correct":21},"财务净现值率小于零",{"id":597,"libraryId":5,"type":35,"typeLabel":36,"stem":598,"options":599,"answer":155,"analysis":32},931064,"价值工程对象选择的方法有( )。",[600,601,603,605,607],{"key":19,"text":86,"correct":25},{"key":23,"text":602,"correct":21},"歌顿法",{"key":27,"text":604,"correct":21},"头脑风暴法",{"key":30,"text":606,"correct":25},"经验分析法",{"key":47,"text":608,"correct":25},"最合适区域法",{"id":610,"libraryId":5,"type":9,"typeLabel":15,"stem":611,"options":612,"answer":23,"analysis":32},931065,"由于业主原因导致承包商自有机械停工，则台班窝工费一般按( )计算。",[613,615,617,619],{"key":19,"text":614,"correct":21},"台班单价",{"key":23,"text":616,"correct":25},"台班折旧费",{"key":27,"text":618,"correct":21},"台班人工费",{"key":30,"text":620,"correct":21},"台班维护费",{"id":622,"libraryId":5,"type":35,"typeLabel":36,"stem":623,"options":624,"answer":74,"analysis":32},931066,"影响抽样误差的因素主要来自于( )。",[625,627,629,631,633],{"key":19,"text":626,"correct":25},"样本容量",{"key":23,"text":628,"correct":21},"变异系数",{"key":27,"text":630,"correct":25},"总体标志值的差异程度",{"key":30,"text":632,"correct":21},"极差",{"key":47,"text":634,"correct":25},"抽样方法",{"id":636,"libraryId":5,"type":9,"typeLabel":15,"stem":637,"options":638,"answer":27,"analysis":32},931067,"下列描述中，符合散布图曲线相关的选项是( )。",[639,641,643,645],{"key":19,"text":640,"correct":21},"x增大时，y也随之增大，即x与y变化趋势相同",{"key":23,"text":642,"correct":21},"x增大时，y反而减小，即x与y变化趋势相反",{"key":27,"text":644,"correct":25},"x开始增大时，y也随之增大，但达到某一值时，随x增大，y却减小",{"key":30,"text":646,"correct":21},"x与y看不出任何相关关系",{"id":648,"libraryId":5,"type":35,"typeLabel":36,"stem":32,"options":649,"answer":660,"analysis":32},931068,[650,652,654,656,658],{"key":19,"text":651,"correct":25},"该工作提前1周完成",{"key":23,"text":653,"correct":25},"在第7周内实际完成的任务量超过计划任务量",{"key":27,"text":655,"correct":25},"第四周停工1周",{"key":30,"text":657,"correct":21},"在第3周内实际完成的任务量比计划任务量少6%",{"key":47,"text":659,"correct":21},"在第5周内实际进度与计划进度一致","ABC",{"id":662,"libraryId":5,"type":9,"typeLabel":15,"stem":663,"options":664,"answer":27,"analysis":32},931069,"FNPV=0，表明项目获利程度( )。",[665,667,669,670],{"key":19,"text":666,"correct":21},"低于基准收益率",{"key":23,"text":668,"correct":21},"高于基准收益率",{"key":27,"text":326,"correct":25},{"key":30,"text":328,"correct":21},[672,675,678,681,684,687],{"id":9,"name":673,"category":7,"favorite":674},"领导干部任职前廉政法规知识测试题",92,{"id":676,"name":677,"category":7,"favorite":9},595,"建筑结构与设备",{"id":679,"name":680,"category":7,"favorite":9},715,"招标采购专业知识与法律法规",{"id":682,"name":683,"category":7,"favorite":9},848,"市政方向-通用基础",{"id":685,"name":686,"category":7,"favorite":8},534,"BIM工程师",{"id":688,"name":686,"category":7,"favorite":8},535]