[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931672":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931672,603,1,"单选题","当利用S曲线比较法将实际进展情况与计划S型曲线进行比较时，如果检查日期实际进展点落在计划S曲线的左侧，则该实际进展点与计划S型曲线的垂直距离表示( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程实际进度拖后的时间",false,{"key":16,"text":17,"correct":14},"B","工程实际进度拖后的任务量",{"key":19,"text":20,"correct":21},"C","工程实际进度超前的任务量",true,{"key":23,"text":24,"correct":14},"D","工程实际进度超前的时间","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]