[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931670":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931670,603,1,"单选题","单代号搭接网络的时间参数计算时，若某项中间工作的最早开始时间为负值，则应当( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将该工作与最后一项工作联系起来",false,{"key":16,"text":17,"correct":18},"B","在该工作与起点节点之间添加虚箭线",true,{"key":20,"text":21,"correct":14},"C","增大该工作的时间间隔",{"key":23,"text":24,"correct":14},"D","调整其紧前工作的持续时间","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]