[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931665":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931665,603,2,"多选题","关于双代号网络图绘制基本规则，下列叙述正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","网络图中不得存在循环回路；",true,{"key":16,"text":17,"correct":18},"B","允许在网络图中出现无箭头的连线或双向箭线；",false,{"key":20,"text":21,"correct":14},"C","一个网络图应只有一个起点节点和一个终点节点；",{"key":23,"text":24,"correct":14},"D","一条箭线加两端的节点只能表示惟一的一项工作；",{"key":26,"text":27,"correct":14},"E","严禁在网络图中出现没有箭尾节点的箭线和没有箭头节点的箭线。","ACDE","1双代号网络图绘制基本规则(一)正确表达工作间的逻辑关系(二)一条箭线加两端的节点只能表示惟一的一项工作(三)网络图中不得存在循环回路(四)网络图中严禁出现双向箭头和无箭头的连线(五)严禁在网络图中出现没有箭尾节点的箭线和没有箭头节点的箭线(六)网络图起始节点有多条外向箭线和终点节点有多条内向箭线的画法(七)箭线交叉(八)一个网络图应只有一个起点节点和一个终点节点",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]