[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931663,603,1,"单选题","为了使工程所需要的资源按时间的分布符合优化目标，网络计划的资源优化是通过改变( )来达到目的的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键工作的开始时间",false,{"key":16,"text":17,"correct":18},"B","工作的开始时间",true,{"key":20,"text":21,"correct":14},"C","关键工作的持续时间",{"key":23,"text":24,"correct":14},"D","工作的持续时间","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]