[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931662":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931662,603,2,"多选题","与横道计划相比，网络计划具有以下主要特点( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","网络计划能够明确表达各项工作之间的逻辑关系",true,{"key":16,"text":17,"correct":14},"B","通过网络计划时间参数的计算，可以找出关键线路和关键工作",{"key":19,"text":20,"correct":14},"C","通过网络计划时间参数的计算，可以明确各项工作的机动时间",{"key":22,"text":23,"correct":14},"D","网络计划可以利用电子计算机进行计算、优化和调整",{"key":25,"text":26,"correct":27},"E","比横道计划直观明了",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]