[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931658":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931658,603,2,"多选题","设备监理单位对成套设备项目设计中交接点复查与核实的重点应为( )等各项衔接关系",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","连接方式",true,{"key":16,"text":17,"correct":18},"B","连接状态",false,{"key":20,"text":21,"correct":14},"C","连接尺寸",{"key":23,"text":24,"correct":14},"D","交接点参数",{"key":26,"text":27,"correct":18},"E","成套设备与外部其他交通路径的接口","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]