[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931646":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":9},931646,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总工期为20天",false,{"key":16,"text":17,"correct":18},"B","关键线路有1条",true,{"key":20,"text":21,"correct":14},"C","关键线路有2条",{"key":23,"text":24,"correct":18},"D","工作H的总时差为1天",{"key":26,"text":27,"correct":18},"E","工作D的自由时差为3天","BDE",{"id":6,"name":30,"category":31,"favorite":32},"质量、投资、进度控制","建筑工程",0]