[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931640,603,1,"单选题","",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分别为1和0",true,{"key":16,"text":17,"correct":18},"B","均为1",false,{"key":20,"text":21,"correct":18},"C","分别为2和0",{"key":23,"text":24,"correct":18},"D","均为0","首先找出关键线路：CEJM。工作A的紧后工作为D，工作D的紧后工作为H、I和J。J为关键工作。工作D和工程J时间间隔为1天。所以工作D的总时差为1。工作A和工作D的时间间隔为0。所以工作A的总时差为1，自由时差为0。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]