[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931637":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931637,603,2,"多选题","某设备安装工程采用总承包发包，设备监理工程师在进度管理中，需审核的承包商文件包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设备安装总进度计划",true,{"key":16,"text":17,"correct":14},"B","总承包商提交的进度报告",{"key":19,"text":20,"correct":14},"C","总承包商提交的进度调整方案",{"key":22,"text":23,"correct":24},"D","设备安装进度管理监理工作细则",false,{"key":26,"text":27,"correct":14},"E","工期索赔报告","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]