[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931636":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931636,603,2,"多选题","在下列实际进度与计划进度的比较方法中，可以从设备工程整体角度反映实际进度偏差的方法有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","匀速进展横道图比较法",false,{"key":16,"text":17,"correct":14},"B","非匀速进展横道图比较法",{"key":19,"text":20,"correct":21},"C","前锋线比较法",true,{"key":23,"text":24,"correct":21},"D","S形曲线比较法",{"key":26,"text":27,"correct":21},"E","“香蕉”曲线比较法","CDE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]