[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931632":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931632,603,1,"单选题","网络计划的工期优化是指( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","寻求网络计划的最短工期",false,{"key":16,"text":17,"correct":18},"B","当计算工期大于要求工期时，通过压缩关键工作的持续时间，寻求满足工期要求的网络计划",true,{"key":20,"text":21,"correct":14},"C","寻求网络计划最短工期的资源均衡",{"key":23,"text":24,"correct":14},"D","寻求网络计划最短工期下的费用最低","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]