[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931631":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931631,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","节点编号不对",false,{"key":16,"text":17,"correct":18},"B","有无箭头的连接",true,{"key":20,"text":21,"correct":14},"C","有循环回路",{"key":23,"text":24,"correct":18},"D","多个起点节点",{"key":26,"text":27,"correct":18},"E","有多余虚工作","BDE","有无箭头的连接----工作F；多个起点节点----①④；有多余虚工作----④-⑥，④-⑤。选项A：圈1、2；选项B：只有一个圈12；选项C：两个圈9；选项D：不存在；选项E：圈3；4。",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]