[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931629":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931629,603,2,"多选题","在项目决策阶段，可作为工程投资确定的重要依据的工程技术文件有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目意向书",true,{"key":16,"text":17,"correct":14},"B","项目建议书",{"key":19,"text":20,"correct":14},"C","可行性研究报告",{"key":22,"text":23,"correct":24},"D","有关设计资料",false,{"key":26,"text":27,"correct":24},"E","工程招标文件","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]