[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931628,603,1,"单选题","在某工程单代号网络计划中，下列说法不正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","至少有一条关键线路",false,{"key":16,"text":17,"correct":18},"B","在计划实施过程中，关键线路始终不会改变",true,{"key":20,"text":21,"correct":14},"C","关键工作的机动时间最小",{"key":23,"text":24,"correct":14},"D","相邻关键工作之间的时间间隔为零","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]