[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931627":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931627,603,1,"单选题","编制设备安装工程概算时，当初步设计深度不够，设备清单不详细，只有主体设备或仅有成套设备重量时，可采用( )编制概算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","概算指标法",false,{"key":16,"text":17,"correct":18},"B","扩大单价法",true,{"key":20,"text":21,"correct":14},"C","预算单价法",{"key":23,"text":24,"correct":14},"D","设备费的百分比法","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]