[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931623,603,1,"单选题","网络计划资源优化中“工期固定一资源均衡优化”的含义是指( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资源有限条件下的最短工期安排",false,{"key":16,"text":17,"correct":18},"B","工期不变条件下的资源均衡安排",true,{"key":20,"text":21,"correct":14},"C","工期最短条件下的资源均衡安排",{"key":23,"text":24,"correct":14},"D","工期最优条件下的资源均衡安排","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]