[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931622":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931622,603,2,"多选题","与网络图相比，横道图的不足有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不便于统计完成计划所需资源的时间分布",false,{"key":16,"text":17,"correct":18},"B","较难判断计划方案优劣",true,{"key":20,"text":21,"correct":14},"C","不便于工序进展状况的检查",{"key":23,"text":24,"correct":18},"D","不能计算各项工作的各类时间参数",{"key":26,"text":27,"correct":18},"E","不能明确显示工作的关键程度","BDE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]