[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931620":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931620,603,1,"单选题","在网络计划工期优化过程中，当出现多条关键线路时，必须( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将各条关键线路的总持续时间压缩同一数值；",true,{"key":16,"text":17,"correct":18},"B","压缩所需资源总量最少的一条关键线路；",false,{"key":20,"text":21,"correct":18},"C","压缩其中一条关键线路的总持续时间；",{"key":23,"text":24,"correct":18},"D","分别将各条关键线路的总持续时间压缩不同的数值。","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]