[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931614":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931614,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作C实际进度拖后，但不影响总工期",false,{"key":16,"text":17,"correct":18},"B","工作D仍有总时差2天",true,{"key":20,"text":21,"correct":14},"C","工作E仍有总时差1天",{"key":23,"text":24,"correct":18},"D","工作G的最早开始时间将会受影响",{"key":26,"text":27,"correct":14},"E","工作H的最早开始时间不会受影响","BD","本图的关键线路为AEHI；工作D原总时差为2天且按时完成任务，所以仍有总时差2天；由于C原有总时差为1天，现拖后2天，所以其紧后工作G的最早开始时间将会受影响，且影响总工期。由于工作E为关键工作，没有总时差；且拖后1天，所肯定要影响工作H的最早开始时间。",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]