[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931597":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931597,603,1,"单选题","应用S形曲线比较法时，通过比较实际进度S形曲线和计划进度S形曲线，可以( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","表明实际进度是否匀速开展",false,{"key":16,"text":17,"correct":18},"B","得到工程项目实际超额或拖欠的任务量",true,{"key":20,"text":21,"correct":14},"C","预测偏差对后续工作及工期的影响",{"key":23,"text":24,"correct":14},"D","表明对工作总时差的利用情况","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]