[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931594":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931594,603,2,"多选题","下列关于双代号时标网络组成的叙述，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实箭线表示实工作",true,{"key":16,"text":17,"correct":18},"B","水平虚箭线表示虚工作消耗的时间",false,{"key":20,"text":21,"correct":14},"C","虚工作的水平段应绘制波形线",{"key":23,"text":24,"correct":18},"D","箭线宜用水平箭线或斜箭线",{"key":26,"text":27,"correct":14},"E","箭线直线段的水平投影长度表示工作的持续时间","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]